Recommendation: That, on the
recommendation of the Director, Development & Compliance & Chief
Building Official, the Civic Administration BE DIRECTED to undertake
the following actions with respect to proposed changes (Program Rules) to the
Feed-in-Tariff (FIT) Program, operated by the Ontario Power Authority (OPA):
a) undertake
the process described in the recommendations below when the Draft FIT Program
Rules (April 5, 2012), which are designed to assist renewable energy project
developers obtain timely Municipal Council Support Resolutions, are finalized
in the very near future; it being noted that if the FIT Program Rules are
substantially changed when finalized, the Civic Administration will revise
these recommendations and resubmit, if required;
b) co-ordinate
and review all requests for a Municipal Council Support Resolution and
determine if the request(s) fall into Category 1 Projects (all rooftop solar
anywhere in London), Category 2 Projects (ground-mounted solar at specific
locations in London) or Category 3 Projects (significant FIT projects, such
as wind, biomass and biogas at specific locations in London);
i)
for
Category 1 Projects, the proposed resolution that the construction and
operation of rooftop solar projects, having little or no potential for
impacts on adjacent properties, be supported without reservation anywhere in
London where permitted by the Province of Ontario’s Feed-In Tariff (FIT)
Program rules be approved, as set out in the Municipal Council Blanket
Support Resolution attached hereto as Appendix “A”;
ii)
for
Category 2 Projects, the proposed resolution that the construction and
operation of ground-mounted solar projects, having little or no potential for
impacts on adjacent properties, be supported at a specific location(s)
identified by the project developer where permitted by the Province
of Ontario’s Feed-In Tariff (FIT) Program rules be approved as at two step
process:
A)
the
Civic Administration prepare a recommendation report to Planning &
Environment Committee commenting on the proposed location; and,
B) if supported by the Civic
Administration, submit a Municipal Council Support Resolution attached
hereto as Appendix “B” as part of the report to Planning & Environment
Committee; and,
iii)
for
Category 3 Projects, the Civic Administration will review and offer
recommendations to Council on the required steps for undertaking these types
of projects and opportunities for a Municipal Council Support Resolution;
c)
co-ordinate
the Municipal Council Support Resolution process through the Land Use
Planning Division; it being noted that liaison will take place with the Civic
Administration from Development & Compliance and Environmental &
Engineering Services; and,
d)
the
Mayor and the City Clerk be authorized to sign any requested Council Resolution
for Category 1 Projects using the Municipal Council Blanket Support
Resolution (Appendix “A”); it being noted that these
recommendations are solely for the purpose of enabling an applicant of the
FIT Program to receive priority points under the new FIT Program rules, and
may not be used for the purpose of any other form of municipal approval in
relation to the application or project or any other purpose;
it being noted that the Planning and
Environment Committee received a communication, dated June 25, 2012, from
Richard Weston, Director of Business Development, QPA Solar Inc., with
respect to this matter. (2012-W12-00)
|