Recommendation: That, on the
recommendation of the Managing Director, Engineering and City Engineer, the
following actions be taken with respect to the appointment of a consultant
for the Dingman Creek Subwatershed Study, climate change update:
a) Delcan
(Consultant), 1069 Wellington Road South, Suite 214, London, ON, N6E 2H6, BE
APPOINTED as Consulting Engineers for the Dingman Creek Subwatershed
Study Update in the amount of $327,159, excluding H.S.T., including
allowances for contingency and provisional items for a physical survey and a Westminster
Wetland Investigation and Water Balance Review, in accordance with Section
15, Clause 15.2(d) of the Procurement of Goods and Services Policy;
b) the
financing for this project BE APPROVED as set out in the Sources of
Financing Report included as Appendix “A” to the associated staff report,
dated October 22, 2012;
c) the
consulting fees for the project identified in (a), above, BE IN ACCORDANCE
with the estimate, on file, which is based upon the Fee Guideline for
Professional Engineering Services, 2006, recommended by the Ontario Society
of Professional Engineers;
d) the
approvals hereby BE CONDITIONAL upon the Corporation entering into a
formal contract with the consultant for the work; and,
e) the
Mayor and the City Clerk BE AUTHORIZED to execute any contract or
other documents, if required, to give effect to these recommendations. (2012-A03-00)
|