a) That,
in accordance with section 291(4)(c) of the Municipal Act, 2001, as amended,
the Water Operating Budget reflecting annual rate increases of 3% for the
2017-2019 period BE READOPTED with no change; it being noted that the Civic
Administration will be reporting back on any adjustments that may be required
as a result of the Clean Water and Wastewater Fund application.
b)
That,
in accordance with section 291(4)9c) of the Municipal Act, 2001, as amended,
the Water Capital Budget for the 2017-2019 period BE READOPTED with no
change; it being noted that the Civic Administration will be reporting back
on any adjustments that may be required as a result of the Clean Water and
Wastewater Fund application.
c)
That
Capital Budget Amendment #1 for the 2020-2025 period (EW3624 Burbrook Main
Upgrade Phase II), in the amount of $2,250,000 (Page 18) BE APPROVED in
principle (subject to annual review).
d)
That
the Water Reserves and Reserve Fund Overviews BE APPROVED; it being noted
that projections are subject to annual review and adjustment.
e)
That,
in accordance with section 291(4)(c) of the Municipal Act, 2001, as amended,
the Wastewater & Treatment Operating Budget reflecting annual rate
increases of 3% for the 2017-2019 period BE READOPTED with no change; it
being noted that the Civic Administration will be reporting back on any
adjustments that may be required as a result of the Clean Water and
Wastewater Fund application.
f)
That
the following Wastewater & Treatment Capital Budget amendments for the
2017–2019 multi-year budget period, representing a $0.2 million decrease in
the Capital Budget, BE APPROVED; it being noted that there is no impact to
wastewater rates from these amendments and the Civic Administration will be
reporting back on any adjustments that may be required as a result of the
Clean Water and Wastewater Fund application:
GROWTH:
i) ES5427
– Pre-assumption Monitoring of SWM Facilities
(Amendment
#2)
($200,000)
(2017)
ii) Timing
changes to Wastewater Growth-Related Capital Projects
(Amendment
#3)
A) ES2475
Dingman Creek Main Channel Remediation Works
($700,000)
(2017)
$700,000
(2018)
B) ES3021
– Land for SWM Facilities
($100,000)
(2017)
$100,000
(2018)
C) ES5428
– Infill & Intensification Nodes (Storm Sewer Servicing)
($689,000)
(2017)
$689,000
(2018)
g)
That,
in accordance with section 291(4)(c) of the Municipal Act, 2001, as amended,
the following actions be taken with respect to the Wastewater & Treatment
Capital Budget:
i) the
revised 2017 Capital Budget BE ADOPTED in the amount of $69,004,000;
ii) the
revised 2018 Capital Budget BE ADOPTED in the amount of $78,137,000; and
iii) the
revised 2019 Capital Budget BE ADOPTED in the amount of $56,067,000.
h)
That
the Wastewater & Treatment Capital Forecast for the 2020-2025 period BE
APPROVED, in principle and with no change (subject to annual review).
i)
That
the Wastewater & Treatment Reserves and Reserve Fund Overviews BE
APPROVED; it being noted that projections are subject to annual review and
adjustment.
j)
That
the Civic Administration BE DIRECTED to update the 20-Year Operating and
Capital Plan Forecast based on the cumulative impacts of the Clean Water and
Wastewater Fund (Phases 1 and 2), Rapid Transit, Development Charge Update,
regulatory changes, optimization programs and use of innovation; it being
noted that these updated Plans will form the basis for the 2020-2023
multi-year budget and rate forecast.
|